Project Delivery

- Publication no: AGPD03-22
- ISBN: 978-1-922700-34-6
- Published: 25 March 2022
- Edition: 3.0
- PDF (free) Download
- View online View guide
Guide to Project Delivery Part 3: Contract Management is concerned with the procurement and management of road construction contracts. It covers in detail, key processes and procedures relating to documentation and contract administration. It also includes a range of sample tools, templates, registers and checklists designed to provide practical support to practitioners working in this field.
Watch a webinar with Colin MacKay, Nigel Powers and Karen Cogo.
Edition 3.0 has been revised to move the Tender and Contract Award Chapters to Part 2 to align with the Planning and Control of Project Delivery.
Changes were also made to the terminology. The word “partnering” was added to reflect the collaborative rather than cooperative nature of work during contracts and projects. The reference to “drawings” was replaced with “digital models” to align with digital engineering practice.
-
-
- 3.1.1 Role of the Principal
- 3.1.2 Role and Responsibilities of the Contract Administrator
- 3.1.3 The Contract Administrator’s Representative
- 3.1.4 The Contract Administrator’s Representative’s Representative
- 3.1.5 The Roles and Responsibilities of the Designer and Contractor
- 3.1.6 Relationships in a Contract
- 3.1.7 Partnering and Collaborative Contracting
-
- 3.3.1 Delegations
- 3.3.2 Execution of the Contract
- 3.3.3 Documents to be Supplied by the Principal and the Contract Administrator
- 3.3.4 Security
- 3.3.5 Insurance
- 3.3.6 Possession of Site
- 3.3.7 Documents to be Supplied by the Contractor
- 3.3.8 Partnering or Start-up Workshop
- 3.3.9 Pre-construction Meeting
-
- 3.13.1 Certificate of Practical/Construction Completion
- 3.13.2 Liquidated Damages
- 3.13.3 Defects Liability
- 3.13.4 Final ‘As-built’ Construction Program
- 3.13.5 Work-as-executed Digital Models or As-built Digital Models
- 3.13.6 Conformance Records
- 3.13.7 Final Statement from the Contractor
- 3.13.8 Final Payment Schedule
- 3.13.9 Final Payment
- 3.13.10 Return of Security
-
-
-
- Appendix B 1.1 Description of the Works
- Appendix B 1.2 Design Features – Usually Applies to Bridgeworks
- Appendix B 1.3 Work not in Contract
- Appendix B 1.4 Working Area
- Appendix B 1.5 Access to Site
- Appendix B 1.6 Schedule of Site Possession
- Appendix B 1.7 Public Utility Adjustments
- Appendix B 1.8 Milestones
- Appendix B 1.9 Concurrent Work
- Appendix B 1.10 Order of Work
- Appendix B 1.11 Changes to QA Model Specifications
- Appendix B 1.12 Materials Supplied by the Principal
- Appendix B 1.13 Historic Buildings
- Appendix B 1.14 Use of Structures by Construction Plant
- Appendix B 1.15 Other Matters
-
-
-
-
-