Test Methods and Specifications

Cover of Earthworks for Bridgeworks
Earthworks for Bridgeworks
  • Publication no: ATS-5110-25
  • Published: 1 December 2025
  • Edition: 1.1

Austroads Technical Specification ATS 5110 sets out the requirements for excavation, backfill associated with bridgeworks, including the construction of cofferdams. If specified, it also applies to other major structures such as culverts with a span exceeding 4.2 m and retaining walls.

It includes requirements for the placement and compaction of general fill and / or select fill adjacent to bridges, which are in addition to the requirements included in the specification for general earthworks.

Refer to ATS 5120 for the requirements for the backfilling of reinforced soil walls.

The technical specification can also be downloaded as a Word document.

Edition 1.1 published December 2025

Edition 1.1 amends:

  • Clause 7.9 – Change of spelling of ‘binding’ to ‘blinding’

Superseded editions

Edition 1.0 published March 2023

  • 1. Scope
  • 2. Referenced Documents
  • 3. Definitions
  • 4. Quality System Requirements
  • 5. Construction in Waterways
  • 6. Cofferdams and Dewatering Systems
    • General
    • Cofferdams
  • 7. Excavation
    • General
    • Preparation of the base of the excavation
    • Blinding layer
  • 8. Backfill
    • General
    • Compaction
  • 9. Drainage Zone Material
  • Annexure A: Summary of Hold Points, Witness Points and Records