B2 activities plus the majority of the following:
Typical Characteristics of Contract Work
When determining the applicable prequalification category, the Participating Agency will consider the predominance of characteristics for each project, rather than considering a single characteristic in isolation. For example; for a roadworks contract to be classified as B3, at least 5 of the 10 typical characteristics for B3 would need to be substantially applicable to the contract concerned.
Typical Features of Structure
- Voided slab superstructures.
- Post tensioned cast in-situ structural elements.
- Complex (ie variable depth) steel girders.
- Major slipform piers.
- Moderately complex geometry and size.
- Cable stayed pedestrian bridges.
Construction Methodology and Site Constraints
- Construction over heavily trafficked roads requiring complex traffic management.
- Top down construction methodology.
- Difficult site access.
- Dewatering required.
- Staged or complex bridge construction sequence (eg: one lane at a time).
- Heavy lifting of prefabricated superstructure into final position.
Foundations
- Foundations which may be complex and/or require deep piling and/or require floating equipment or temporary bridges.
- Include cast insitu piles, which may include simple dry rock sockets.
Bearings/Joints and Ancillary Components
- Expansion joint accommodates large movement (typically > 100 mm).
- Finger Joints designed for large movements.
- Spherical bearings and heavily loaded pot bearings.
Environment, Community and Stakeholder Management
- Moderate to complex community/stakeholder interfaces and project management aspects.
- Consultant team coordination and/or management.
- Design management.
- Moderate to complex environmental management waterway barrier, low flow channels.
Minimum Requirements: Company Experience
Minimum Period of Operation (approximate)
- 4 years as a head contractor.
Experience in Successfully Delivering Contracts
- Sound experience with the successful completion of at least two B2 projects in the last 5 years.
- At least one of the nominated projects must have been tendered by a Participating Agency or on behalf of a Participating Agency.
Demonstrated Performance
- The Applicant has not been responsible for a failure to complete a contract.
- Good general performance on contracts relevant to B2.
Minimum Requirements: Company Resources and Technical Capability
Organisational / Managerial Structure
- The Applicant’s company structure and management structure are appropriate for the scale of projects to be undertaken in the applicable category.
Personnel
- The Applicant has sufficient personnel available to undertake B3 projects.
Key Personnel Active in the Entity's Roadworks Operations
- Key personnel have the qualifications and experience relevant to the duties and responsibilities of their nominated position.
- At least 3 of the senior personnel are Professional Civil Engineers with at least 5 years relevant experience in road / bridge works.
- At least half of the key professionals/para-professionals and key supervisory staff have 5 years construction experience and at least 2 years experience each in B2-type contracts.
Plant and Equipment
- The Applicant has demonstrated the capability to provide plant and equipment required to properly resource B3 contracts.
Minimum Requirements: Management Systems
Quality Management
- Third party Certified to AS/NZS ISO 9001 by a JAS-ANZ accredited conformity assessment body.
- Satisfactory corporate quality policy and example quality plans and ITP plans.
- Evidence of successful utilisation of the QMS on relevant projects.
- No unresolved major non-conformances from its certifying body.
Third party certificates must state that the certification specifically applies to road / bridge construction. A reference to other categories alone (eg civil construction) is insufficient.
Work Health and Safety (WHS)
- Third party Certified to AS/NZS 4801 or to ISO 45001 by a JAS-ANZ accredited conformity assessment body.
- Satisfactory corporate WHS policy and example WHS plans.
- Evidence of successful utilisation of the WHS system on relevant projects.
- No unresolved major non-conformances from its certifying body.
- No unresolved Improvement Notices or Infringement Notices from a regulatory body.
- Lost Time Injury Frequency Rate for the past three years are similar to or less than industry averages.
Accreditation under the Australian Government’s Building and Construction WHS Accreditation Scheme is deemed to satisfy the WHS requirement for prequalification at all levels.
The International Standard on Occupational Health and Safety (OHS) ISO 45001:2018 was published by Standards Australia as a joint Australian/New Zealand standard in October 2018.
Environmental Management Systems (EMS)
- Third party Certified to AS/NZS ISO 14001 by a JAS-ANZ accredited conformity assessment body.
- Satisfactory corporate environmental policy and example environmental management plans.
- Evidence of successful utilisation of the EMS on relevant projects.
- No unresolved major non-conformances from its certifying body.
- No unresolved Improvement Notices or Infringement Notices from a regulatory body.
Traffic Management
- Satisfactory system in place for the management of traffic at worksites through properly trained and accredited in-house resources or established sub-contract arrangements.
- Satisfactory example traffic management plan appropriate to the category applied for.
Subcontractor Management
- Satisfactory approach to the management of subcontractors and evidence of fair dealing with subcontractors.
- Referee comments are generally positive and no issues have been raised regarding subcontractor management.
Management of the Relationship with the Client
- Has successfully participated in partnering / client relationship management at a level relevant to the category applied for. Demonstrates a positive attitude and willingness.
Community/Stakeholder Engagement
- Evidence of successful community/stakeholder engagement activities on relevant past projects.